To amend sections 122.086, 122.087, 122.089, | 1 |
122.0810, 122.0812, 122.0814, 122.0817, and | 2 |
122.0819 of the Revised Code to require the | 3 |
Director of Development to adopt rules regarding | 4 |
the annual competitive process for the Job Ready | 5 |
Site Program. | 6 |
Section 1. That sections 122.086, 122.087, 122.089, 122.0810, | 7 |
122.0812, 122.0814, 122.0817, and 122.0819 of the Revised Code be | 8 |
amended to read as follows: | 9 |
Sec. 122.086. (A) There is hereby created the job ready site | 10 |
program to provide grants to pay for allowable costs of eligible | 11 |
applicants for eligible projects. The program shall be | 12 |
administered by the department of development | 13 |
14 | |
grants shall be awarded through one of the following two | 15 |
processes: | 16 |
| 17 |
to 122.0811 | 18 |
| 19 |
20 |
(B) The annual competitive process shall be administered by | 21 |
the department of development pursuant to rules adopted by the | 22 |
director of development under Chapter 119. of the Revised Code. | 23 |
The rules shall not establish criteria for the receipt of grants | 24 |
that have the effect of excluding applications for grants from any | 25 |
county of the state. | 26 |
(C) The discretionary process shall be administered by the | 27 |
department of development pursuant to guidelines established by | 28 |
the director of development. | 29 |
Sec. 122.087. The director of development shall establish an | 30 |
annual competitive process for making grants described in section | 31 |
122.086 of the Revised Code in accordance with rules adopted under | 32 |
that section. | 33 |
may be distributed as grants each year under the job ready site | 34 |
program shall be distributed under the annual competitive process. | 35 |
Sec. 122.089. An eligible applicant shall provide all of the | 36 |
following on the annual competitive process application: | 37 |
(A) Contact information for the eligible applicant; | 38 |
(B) A legal description of the property for which the grant | 39 |
is requested; | 40 |
(C) A summary of the proposed eligible project that includes | 41 |
all of the following: | 42 |
(1) A general description of the eligible project, including | 43 |
individuals, organizations, or other entities that will play a | 44 |
critical role in the implementation of the project; | 45 |
(2) An explanation of the need for the eligible project, and | 46 |
the predicted economic impact; | 47 |
(3) An explanation of the need for a grant from the job ready | 48 |
site program; | 49 |
(4) The commitments required pursuant to division (A)(3) of | 50 |
section 122.0815 of the Revised Code. | 51 |
(D) A detailed summary of costs for the eligible project, | 52 |
including supporting documents for cost estimates; | 53 |
(E) Sources of funding for the eligible project, including | 54 |
documentation verifying the status of those funds; | 55 |
(F) Summary results of preliminary engineering studies and | 56 |
environmental reviews, if any have been conducted; | 57 |
(G) A comprehensive marketing plan detailing how the eligible | 58 |
project will be marketed upon completion, if appropriate; | 59 |
(H) Copies of resolutions or ordinances related to the | 60 |
eligible project, including resolutions or ordinances adopted by | 61 |
the political subdivision with jurisdiction over the geographic | 62 |
area in which the eligible project is located; | 63 |
(I) Any other information the director of development | 64 |
requests on the application form. | 65 |
Sec. 122.0810. (A) Each application for a grant pursuant to | 66 |
the annual competitive process received by a district public works | 67 |
integrating committee shall be evaluated by the executive | 68 |
committee of the district committee. In conducting the evaluation, | 69 |
the executive committee shall determine whether the application | 70 |
for the proposed eligible project is complete and whether the | 71 |
project meets the requirements of section 122.0815 of the Revised | 72 |
Code. If the application is complete and the eligible project | 73 |
meets the requirements of section 122.0815 of the Revised Code, | 74 |
the executive committee shall prioritize the eligible project | 75 |
pursuant to section 122.0816 of the Revised Code and pursuant to | 76 |
local priorities, as those priorities are determined by the | 77 |
executive committee, with all other eligible projects with | 78 |
complete applications that meet the requirements of section | 79 |
122.0815 of the Revised Code. If the application is incomplete or | 80 |
the project does not meet the requirements of section 122.0815 of | 81 |
the Revised Code, the executive committee shall notify the | 82 |
applicant of the deficiencies and the period of time the applicant | 83 |
has to correct the deficiencies and submit the corrections to the | 84 |
executive committee. Failure to correct deficiencies within the | 85 |
time designated by the executive committee shall disqualify the | 86 |
project from consideration for a grant during the annual | 87 |
competitive process for that year. | 88 |
The executive committee, by the affirmative vote of a | 89 |
majority of all its members, shall select up to three eligible | 90 |
projects from the projects it has prioritized each year pursuant | 91 |
to the annual competitive process. The executive committee shall | 92 |
forward the applications and any accompanying information for each | 93 |
of the selected eligible projects to the department of development | 94 |
in the time and manner required by the | 95 |
the annual competitive process for the job ready site program. | 96 |
(B) For a district public works integrating committee that | 97 |
does not have an executive committee, the full committee shall | 98 |
perform the functions assigned to the executive committee under | 99 |
section 122.0816 of the Revised Code and division (A) of this | 100 |
section. | 101 |
(C) An executive committee, or a district committee that does | 102 |
not have an executive committee, may appoint a working group of | 103 |
committee members and staff to perform the functions of those | 104 |
committees as provided in this section. | 105 |
Sec. 122.0812. The director of development shall establish a | 106 |
discretionary process that permits the director to make grants | 107 |
described in section 122.086 of the Revised Code in situations | 108 |
that include those in which the timing of a proposed eligible | 109 |
project is such that the annual competitive process is not | 110 |
suitable. The director, as part of the guidelines established for | 111 |
the discretionary process for the job ready site program, shall | 112 |
establish all the procedures and requirements governing | 113 |
application for the discretionary grants. | 114 |
Sec. 122.0814. If the controlling board approves a grant for | 115 |
an eligible project pursuant to the annual competitive process or | 116 |
the discretionary process, the director of development shall enter | 117 |
into an agreement with the eligible applicant to provide the grant | 118 |
for the project. The agreement shall be executed prior to the | 119 |
payment or disbursement of any funds under the grant and shall | 120 |
contain the following provisions: | 121 |
(A) A designation of a single officer or employee of the | 122 |
eligible applicant who will serve as the manager of the eligible | 123 |
project; | 124 |
(B) A detailed description of the scope of the work required | 125 |
under the eligible project, including anticipated sources and uses | 126 |
of funds; | 127 |
(C) A designation of the percentage of the estimated total | 128 |
cost of the project for which the grant will provide funding, | 129 |
which shall not exceed seventy-five per cent of the cost; | 130 |
(D) Provisions for the recovery by the department of | 131 |
development of grant funds for failure to meet the terms of the | 132 |
agreement; | 133 |
(E) A requirement that annual reports be made by the eligible | 134 |
applicant on the progress of the eligible project and any other | 135 |
information about the status of the project as required by the | 136 |
guidelines and rules established for the job ready site program; | 137 |
(F) Any other provisions the director determines necessary. | 138 |
Sec. 122.0817. In accordance with the guidelines established | 139 |
to govern the discretionary process and the rules adopted to | 140 |
govern the annual competitive process for the job ready site | 141 |
program, the director of development shall publish an annual | 142 |
report that includes the following: | 143 |
(A) Details on each grant awarded pursuant to the program; | 144 |
(B) The status of projects funded in previous years; | 145 |
(C) The amount of grants awarded for projects in economically | 146 |
distressed areas and, to the extent possible, the impact of those | 147 |
grants in those areas. | 148 |
Sec. 122.0819. The | 149 |
govern the annual competitive process for the job ready site | 150 |
program may provide for recovery of the costs, or a portion | 151 |
thereof, incurred by district public works integrating committees | 152 |
and executive committees in conducting their duties under the | 153 |
program. | 154 |
Section 2. That existing sections 122.086, 122.087, 122.089, | 155 |
122.0810, 122.0812, 122.0814, 122.0817, and 122.0819 of the | 156 |
Revised Code are hereby repealed. | 157 |